Explain the concept of earned value management (EVM) in project cost control.
Earned Value Management (EVM) is a project management technique that integrates scope, schedule, and cost data to assess project performance and progress. It provides a quantitative measurement of project performance, helping project managers to analyze and control costs effectively. The key components of EVM include Planned Value (PV), Earned Value (EV), and Actual Cost (AC).
- Planned Value (PV):
- PV represents the authorized budget assigned to the work to be accomplished up to a specific point in time.
- It is the estimated value of the work that should have been completed based on the original project plan.
- PV is often expressed in terms of time, usually in terms of weeks or months.
- Earned Value (EV):
- EV represents the value of the work actually performed up to a specific point in time.
- It is measured in the same terms as PV, providing a direct comparison between planned and actual progress.
- EV is determined by assessing the completion of specific project tasks or deliverables.
- Actual Cost (AC):
- AC represents the total cost incurred in accomplishing the work performed up to a specific point in time.
- It includes all costs associated with the project, such as labor, materials, equipment, and overhead.
Once PV, EV, and AC are determined, several performance metrics can be calculated to assess the project's health:
- Cost Performance Index (CPI):
- CPI is calculated by dividing EV by AC (CPI = EV / AC).
- A CPI value greater than 1 indicates that the project is under budget, while a value less than 1 suggests that the project is over budget.
- Schedule Performance Index (SPI):
- SPI is calculated by dividing EV by PV (SPI = EV / PV).
- An SPI value greater than 1 indicates that the project is ahead of schedule, while a value less than 1 suggests that the project is behind schedule.
- Variance at Completion (VAC):
- VAC is calculated by subtracting the Budget at Completion (BAC) from the Estimate at Completion (EAC) (VAC = BAC - EAC).
- A positive VAC indicates that the project is expected to be under budget, while a negative VAC suggests that the project is expected to be over budget.
- Estimate at Completion (EAC):
- EAC represents the expected total cost of completing the project based on performance to date.
- EAC can be calculated in various ways, such as EAC = BAC / CPI or EAC = AC + (BAC - EV).